Harris Park costs rising to $14 million

Interesting how the NY Post can get this exclusive, but the community can not get any answers.

Below is the article.  Here is the PDF for the article: Harris Park $14 M Jan 2010

————————

New York Post – Updated: Thu., Jan. 28, 2010, 1:16 PM


Bronx field now city’s $14M

blunder land

By RICH CALDER, Posted: 2:31 AM, January 19, 2010

A city plan to rebuild one of The Bronx’s biggest sports fields has morphed into a money pit for taxpayers.

Workers renovating Harris Field in Bedford Park recently uncovered contaminated soil under the playing surfaces, helping push the anticipated cost to nearly $14 million, city officials told The Post.

The price tag for the renovation had already gone from the $6.6 million announced in 2007 to $8.7 million, records show.

Now the Parks Department is confirming that it has to add another $5.2 million for cleanup because of the high levels of lead unearthed while workers were preparing to install drainage-system tanks needed to restore the popular park’s six playing fields.

Harris Field used to be part of a reservoir before the city acquired the 15-acre site in 1917.

Department spokeswoman Vickie Karp said it is believed that the park was created with “the use of incinerator ash as fill, which would explain the presence of lead.”

The original playing fields at the park were grass, but the city plans to cover two with synthetic turf.

A Parks Department official wishing to remain anonymous said that contamination wouldn’t be an issue if all the fields were going to be grass but that replacing two with turf requires digging deeper to install the drainage tanks. Karp says this is untrue.

A fiscal 2008 mayoral report showed the Parks Department topped city agencies in cost overruns with projects costing an average of 50 percent more than the original contract price. The city average was 17 percent.

Harris Field is in line to rise by more than 110 percent.

“The project shows just how poorly the city does its due diligence on parks projects,” said Geoffrey Croft, of the nonprofit group New York City Park Advocates, when told of the costs.

The project’s long delays are crippling a popular Little League that plays there.

“The Parks Department only cares about construction, not children,” said Don Bluestone, executive director of the Mosholu Montefiore Community Center.

Bluestone said the nonprofit group’s youth baseball league has gone from 1,000 players to 500 since construction began. He ripped the department for closing the entire park and relocating the league miles away to parks filled with drug dealers and plagued by flooding.

The city’s Web site says construction will be complete by the spring, but Bluestone was preparing to have his league play elsewhere this season.

rich.calder@nypost.com

NEW YORK POST is a registered trademark of NYP Holdings, Inc. (nypost.com , nypostonline.com , and newyorkpost.com are trademarks of NYP Holdings, Inc.), Copyright 2009 NYP Holdings, Inc. All rights reserved. Privacy | Terms of Use

Jan
18th

MINDS IN THE GUTTER seeks submissions

MINDS IN THE GUTTER call for submissions seeks designs for stormwater management in the public right-of-way for juried exhibition and resource guide.

Minds in the Gutter, a project of the Stormwater Infrastructure Matters (SWIM) Coalition, is currently accepting submissions for innovative design solutions that manage runoff from roadways within the public right of way (that’s public space, streets and sidewalks). Submissions must be received before 5pm on February 15, 2010. Details for submitting your project can be found online at  www.mindsinthegutter.org.

Every time it rains in New York City, our combined sewer system gobbles up stormwater running off all hard surfaces – roadways, sidewalks, rooftops and parking lots – into the same network of pipes that carry our sewage. This system quickly reaches capacity, and the stormwater and sewage overflow into local waterways on the order of 27 billion gallons per year. This limits how New Yorkers can safely access the waterfront, and impairs our estuary ecosystem. It’s also a waste! Almost 30% of NYC’s surface is made of streets and sidewalks that contribute to this problem.

Kate Zidar of SWIM asks, “How can we utilize the existing 6K miles of roadway and accompanying 12K miles of sidewalk as an opportunity for stormwater management in NYC?”

Submissions will be reviewed by an esteemed panel of judges from city and state agencies as well as academia and the private sector. The results will be exhibited in April 2010 and will be included in a resource guide for print and online distribution. Above all, through this process we hope to create a collaborative of bright minds in the gutter.

About us:

Storm Water Infrastructure Matters (S.W.I.M.) is a coalition dedicated to ensuring swimmable waters around New York City through natural, sustainable storm water management practices in our neighborhoods.

swimmablenyc@gmail.com